Široké spektrum odborných článkov a prezentácie spoločností, odborníkov pôsobiacich v oblasti stavebníctva, dopravy, strojárstva, ťažby surovín a environmentálnych technológií vo všetkých odvetviach priemyselnej výroby.

Rehabilitation of Camps Bay Drive in Cape Town with Wirtgen Cold Recycling Technologies


Rehabilitation of Camps Bay Drive in Cape Town with Wirtgen Cold Recycling Technologies

Camps Bay Drive is a major scenic route within the  City of Cape Town and provides access to Camps Bay and Hout Bay. Based  on the project brief and geometric analysis, Camps Bay Drive required  widening to safely accommodate the high volumes of tourists and MyCiti  bus traffic. In order to minimize the impact on traffic, the design  brief targeted construction outside the summer peak tourist season and  also required investigation into shortened construction periods. The key  role was played by Wirtgen cold recycling technologies. In action: the  mobile cold recycling mixing plant KMA 200.

The South African metropolis has large volumes of Reclaimed Asphalt  (RA) stockpiled from numerous maintenance works undertaken around the  City. This material has generally been used for hard stand areas and  shoulder construction, In order to reuse this high quality material,  WorleyParsons was tasked to investigate a more efficient and sustainable  use for this material. For this reason, the use of a foamed bitumen  technology was investigated and the base layer on Camps Bay Drive was  constructed using 100% RA as a foamed Bitumen Stabilise Base (BSM) base  layer.

Wirtgen KMA 200 mixes high quality recycling material

Originally, the project consisted of localized road widening to  accommodate the proposed MyCiti buses however due to the large volume  and sizes of the proposed buses, a geometric analysis resulted in the  entire portion of the road being widened by 1,4 m. The proposed pavement  design involved a light rehabilitation with the widening area requiring  full depth construction however during construction, numerous weak  horizons were discovered along the road. The pavement design implemented  for construction involved the following:

  • 50 mm AE-2 Asphalt Surfacing 
  • 200 mm Foamed BSM 1 Base 
  • 150 mm G5 Subbase, natural gravel 
  • 150 mm G7 Selected Subbase, pioneer rock layer  
  • In-situ 

The project was divided into three construction sections. Section 1  from Geneva Drive to Prima Avenue, Section 2 from Prima Avenue to  Rontree Avenue and Section 3 from Rontree Avenue to Houghton Road. 

In order to ensure more uniformity and better quality of the mix, a  static mobile mixing plant was specified for production of the BSM.

Proper Recipe is decisive 

Power Construction was appointed to carry out the construction of  the works with Milling Techniks carrying out the production of the BSM  using their Wirtgen KMA 200.

At the Ndabeni Roads and Stormwater Depot in Maitland, the Wirtgen cold recycling mixing plant KMA 200 quickly and reliably produced the BSM mix.

At the Ndabeni Roads and Stormwater Depot in Maitland, the Wirtgen  cold recycling mixing plant KMA 200 quickly and reliably produced the  BSM mix. 

During construction, the stockpiled RA was sent for technical  testing at BSM Laboratories in Durban. The design was carried out on  three design options using the two dedicated stockpilThe project was  divided into three construction sections. Section 1 from Geneva Drive to  Prima Avenue, Section 2 from Prima Avenue to Rontree Avenue and Section  3 from Rontree Avenue to Houghton Road.es of materials from two sources  which were created for the project by the City. The design options  included:

  • 100% Reclaimed Asphalt 
  • 100% Reclaimed Asphalt with 10 % crusher dust  
  • 100% Reclaimed Asphalt with 25 % G4 gravel material  

Based on the results obtained, the most cost effective option to  yield a BSM 1 was the 100% Reclaimed Asphalt mix design using 2.1 %  foamed bitumen with 1 % cement.

The batching plant was set up at the Ndabeni Roads and Stormwater  depot in maitland. The depot provided sufficient space to establish the  KMA 220 as well as allowing for the stockpiling of the unprocessed RA,  screened RA and processed BSM. The specification called for crushing of  the RA to remove the oversized fractions. An alternate proposal in the  form of screening the material to minus 19 mm in place of crushing the  material by the contractor was accepted provided the fines fraction  (0.075 mm) met the specification of 4 %. This was monitored for the  duration of the project with a fines fraction of between 3 % and 4 %  recorded. The screened RA was processed using the KMA to form a BSM 1  which was stockpiled for up to 7 days at the depot

In order to ensure an adequate quality of the BSM and consistency  within the mixing process, Power Construction, Milling Techniks and  WorleyParsons created a quality system tailored for the BSM production  using the KMA. This was implemented to ensure the mix met the BSM 1  specification throughout the project. Once the BSM was produced, the  material was either placed on site immediately or protected and  stockpiled at the Ndabeni Depot.

BSM quality check before paving is mandatory

The BSM was paved using a heavy duty tracked paver from Power Construction in two 100 mm thick layers in the same process. 

The process used to get the required 100 % Minimum Dry Density (MDD) compaction was as follows:

  • Paving 100 mm thick BSM layer and allowing for bulking of 30 to 40 mm 
  • Applying primary compacting using a 12 t tandem drum roller 
  • Paving the second 100 mm thick BSM layer on to the lower half of the layer 
  • Applying primary compaction using a 12 t tandem drum roller 
  • Applying final compaction using two pneumatic tire rollers (27 t PTR) until compaction was achieved. 

Before starting with paving and compaction, a testing of the BSM was  undertaken by Soillab who established a testing rig in accordance with  the TG2, 2009 specification. Acceptance control was carried out on the  Indirect Tensile Strength (ITS) and MDD taken from the batching plant  and site samples.

The proper recipe and professional BSM producing of the Wirtgen cold recycling mixing plant were the key factors for a successful project. Immediately after paving with a Vögele paver and compaction with Hamm rollers, parts of Camps Bay Drive could be reopened to traffic.

The proper recipe and professional BSM producing of the Wirtgen  cold recycling mixing plant were the key factors for a successful  project. Immediately after paving with a Vögele paver and compaction  with Hamm rollers, parts of Camps Bay Drive could be reopened to  traffic. 

The three sections identified were constructed using similar  techniques, however in Section 1 and 3, the BSM was opened to traffic  immediately after construction and in some cases 24 hours after  construction.

Project provides important insights for cold recycling applications

The Camps Bay Drive rehabilitation project allowed for numerous  lessons when dealing with BSM’s and more particularly 100 % RA BSM’s.  The following lessons were learnt during the project:

  • Static mobile mixing of BSM’s should be undertaken in the summer  months in the Western Cape region due to the weather conditions. Low  temperatures and high moisture contents result in a poorer quality  product. 
  • An impact crusher should be used to crush the oversized RA. This may  create more fines in the mix as well as reduce the need for stockpiling  of the oversized RA 
  • Planning and training of the operators prior to the trial section is  crucial as this product is not an asphalt material and different  placement and compaction methods apply 
  • The 100 RA BSM has voids within the mix and hence when inclement  weather is eminent, the BSM should be sealed to prevent the ingress of  water 

Cold recycling with foamed bitumen: top quality at reduced cost

The following positives were established during the product when using the 100 % BSM:

  • The design is very versatile and minor changes to the RA and mix  design do not have a significant effect on the quality of the BSM 
  • The material behaves extremely well under early trafficking 
  • There is a large cost saving when using the 100 % TA which amounted to  approx. 2,95 Euro per m². This cost only includes the material cost  saving and not additional traffic accommodation and time cost savings 
  • The cost could be further reduced by producing the material closer to  the site or mass producing the material as the greatest cost component  of the BSM production is the haul of the RA and BSM to the site 

Overall, the project was a major success. During the project,  approximately 8,150 t of RA (4,200 m³) was processed using 165 t of  bitumen and 78 t of cement. Using the RA within the pavement structure  provides a much more cost effective and sustainable solution for the  future with depleting aggregate resources.

http://www.wirtgen-group.com